Location

STEW 206

Session Number

67

Session Title

Design and Construction Updates on the Ohio River Bridges

Track Title

Design and Construction

Event Description/Abstract

This presentation will focus on the I-65 cable-stay bridge construction on the Ohio River Bridges Louisville Downtown Crossing project. The presentation will include the overall bridge progress to date, as well as some project issues, including design, construction, and material procurement challenges addressed by the project team.

Share

COinS
 
Mar 11th, 12:00 AM

Cable-Stay Bridge Construction and Progress

STEW 206

This presentation will focus on the I-65 cable-stay bridge construction on the Ohio River Bridges Louisville Downtown Crossing project. The presentation will include the overall bridge progress to date, as well as some project issues, including design, construction, and material procurement challenges addressed by the project team.