The new diverging diamond interchange (DDI) that opened in October 2014 is the first DDI to be constructed in the state of Indiana. This presentation will cover the basic concept, design benefits and challenges, signalization, and lessons learned, as well as report on how well the new interchange is performing now that construction is complete.

Session Number

126

Session Title

Diamond Interchange Designs: Selection, Implementation and Performance

Track Title

Traffic Operations

Location

STEW 218AB

Date of Version

March 2015

Start Date

3-11-2015 12:00 AM

Share

COinS
 
Mar 11th, 12:00 AM

I-69 at SR 1/Dupont Road: Diverging Diamond Interchange

STEW 218AB

The new diverging diamond interchange (DDI) that opened in October 2014 is the first DDI to be constructed in the state of Indiana. This presentation will cover the basic concept, design benefits and challenges, signalization, and lessons learned, as well as report on how well the new interchange is performing now that construction is complete.