US 41 Crack and Seat Case Study: A Practical Design

Track Title

Pavements

Event Description/Abstract

Crack and seat is one of the most cost-effective pavement rehabilitation techniques for existing old concrete with major distresses such as D cracking and joint failures. Using the MEPDG, INDOT saved $20 million from its proposed $33 million budget for this project.