A bridge replacement project on SR 337 over Lost River encountered karst features during foundation design, which ended up altering the preliminary span arrangement and overall bridge length. Through geophysical assessment, a large void was discovered under the bridge location, particularly the preliminary pier location. Construction updates, lessons learned, and perspectives on project challenges and solutions will be shared by a bridge designer and consultant project manager.
Session Number
91
Session Title
Oh Karst! Lost River Bridge Replacement
Track Title
Bridges
Location
STEW 206
Date of Version
March 2023
Start Date
3-15-2023 3:00 PM
End Date
3-15-2023 3:50 PM
Oh Karst! Lost River Bridge Replacement
STEW 206
A bridge replacement project on SR 337 over Lost River encountered karst features during foundation design, which ended up altering the preliminary span arrangement and overall bridge length. Through geophysical assessment, a large void was discovered under the bridge location, particularly the preliminary pier location. Construction updates, lessons learned, and perspectives on project challenges and solutions will be shared by a bridge designer and consultant project manager.