The construction of the I-69 Section 5 roadway included the rehabilitation of several existing metal and concrete culvert crossings under the SR 37 alignment. The option for replacement for many was deemed impractical during earlier assessment inspections. This presentation explores the use and viability of the trenchless centrifugally cast geopolymer lining option on several of the more deteriorated culverts.

Session Number

121

Session Title

The Renewal of I-69 Section 5 CMP Culverts With an Innovative Spray-On Geopolymer Mortar

Track Title

Maintenance & Operations

Location

STEW214CD

Date of Version

March 2019

Start Date

3-6-2019 2:00 PM

End Date

3-6-2019 2:50 PM

Share

COinS
 
Mar 6th, 2:00 PM Mar 6th, 2:50 PM

Geopolymer Mortar System for Structural Rehabilitation/Repair of Sewer and Storm Infrastructure

STEW214CD

The construction of the I-69 Section 5 roadway included the rehabilitation of several existing metal and concrete culvert crossings under the SR 37 alignment. The option for replacement for many was deemed impractical during earlier assessment inspections. This presentation explores the use and viability of the trenchless centrifugally cast geopolymer lining option on several of the more deteriorated culverts.