Abstract
In 2018, portions of I-65 were closed in Indianapolis to construct seven bridge rehabilitations from downtown north to I-465. This presentation discusses the challenges and opportunities related to an interstate closure, including reasons behind INDOT’s decision to close I-65. Highlights include design, project delivery, and construction elements implemented into the contract. Best practices and guidelines for which types of projects could consider closure as a viable MOT (maintenance of traffic) scheme will be covered.
Session Number
26
Session Title
I-65 Closure: Saving Time While Enhancing Safety
Track Title
Maintenance & Operations
Location
STEW214CD
Date of Version
March 2019
Recommended Citation
Muellner, Kyle; Reilman, Jim; and Heustis, Tom, "I-65 Downtown Closure: Saving Time, Enhancing Safety" (2019). Purdue Road School. 24.
https://docs.lib.purdue.edu/roadschool/2019/presentations/24
Start Date
3-5-2019 1:00 PM
End Date
3-5-2019 1:50 PM
I-65 Downtown Closure: Saving Time, Enhancing Safety
STEW214CD
In 2018, portions of I-65 were closed in Indianapolis to construct seven bridge rehabilitations from downtown north to I-465. This presentation discusses the challenges and opportunities related to an interstate closure, including reasons behind INDOT’s decision to close I-65. Highlights include design, project delivery, and construction elements implemented into the contract. Best practices and guidelines for which types of projects could consider closure as a viable MOT (maintenance of traffic) scheme will be covered.