Abstract

INDOT came out with specifications for a very early strength concrete to use on bridge deck overlays. This concrete is fast setting, which allows overlays to be performed over a weekend and benefits the traveling public with a short duration of traffic interference. Cure time to reach the strength requirement is 3 hours. E&B Paving performed the first application with the new spec on August 26, 2018. Many changes were also made to the INDOT Specification Section 722.

Session Number

73

Session Title

Latex-Modified Concrete: Very Early Strength (LMC-VEs)

Track Title

Bridges

Location

STEW206

Date of Version

March 2019

Streaming Media

 
Media is loading

Start Date

3-6-2019 1:00 PM

End Date

3-6-2019 1:50 PM

Share

COinS
 
Mar 6th, 1:00 PM Mar 6th, 1:50 PM

Latex Modified Concrete - Very Early Strength

STEW206

INDOT came out with specifications for a very early strength concrete to use on bridge deck overlays. This concrete is fast setting, which allows overlays to be performed over a weekend and benefits the traveling public with a short duration of traffic interference. Cure time to reach the strength requirement is 3 hours. E&B Paving performed the first application with the new spec on August 26, 2018. Many changes were also made to the INDOT Specification Section 722.